Window, Mechanical, Electrical and Plumbing Day 3

Despite the rain today, they were able to get some more work done. They finished the roof, which we were surprised to see:









In addition to the roof, it looks like they finished most of the HVAC and plumbing today. They finished roughing in our shower plumbing and they have had it filled with water for the last couple days to make sure there are no leaks (it passed).

 They also installed our fireplace:

And they did some touch up framing as well. One of our closets was in the wrong place and that is now fixed. And the two remaining windows were cut to the right size so hopefully we will see those go in soon:

Maybe you noticed in some of the other pictures that there was a bob cat dumping something into our basement, there were actually a lot of people out there working on the house when we arrived (which was 7:00pm):

They were dumping gravel into the basement to prep for the concrete floor to go in. I tried to take a picture of this, but it didn't work out all that well cause it was really dark:

They didn't get much of this done, but it is a good sign that we will see our basement floor (and probably garage floor) go in soon. We will go back out tomorrow to see if they are still working on this or not.